Let there be heat!

First deputy akim of the region Dyusenbai Turganov held a meeting in the regional akimat. The theme was preparation for the heating season.  The head of the Department of Energy and Public Utilities Yermurat Nurkhanov reported there.

“Today, preparation of the buildings for the heating season is nearing completion. As part of preparation for the heating season 2017-2018 it is planned to repair 33 units of the main equipment. Nowadays, 16 facilities have been already repaired, 14 ones are being repaired. The work is according to the schedule”, he said.

“One of the steam boilers was completely repaired, the second one was completed by 89%. In addition, repair of three hot water boilers is nearing completion”, akim of Aksu Nurlan Dyusimbinov said. He assured the first deputy akim of the region that Aksu residents would not have problems with heating and hot water.

Dyusenbai Turganov was concerned about the state of preparation of social facilities for the winter and charged that all buildings would be prepared until September 15. Three cities of the region will be heated from the beginning of next week and areas – as the necessity arises taking into account the weather conditions.

The chief power engineer of the region told that work in the boiler houses of the social facilities had been almost completed by 100%, except for Birlikskaya school in Bayanaul area and four schools in Zhelezinka area, where modular boiler houses would be installed and transferred to the private company for trust management. Akim of Bayanaul area Orazgeldy Kairgeldinov said that the heat transport system would be repaired until the end of this week. Deputy akim of Zhelezinka area Ayan Beisekin said that installation works in the boiler-houses had been completed. Today there is start-up and commissioning works.

The head of the Department of Energy also reported that as of August 1 the debt of consumers for communal services was more than KZ 2.6 bln. He noted that the issue of debt for consumed heat and light influenced on preparation of the energy-supplying organization for the heating season. Yermurat Nurkhanov told participants of the meeting about the algorithm of debt collection. According to the algorithm, regional departments should choose a responsible person, who will monitor the debt of the subordinate organizations. Having compiled all information, he has to give it to the monopoly enterprise and it provides the information to the Department of Energy. The Department of Energy and Public Utilities will consider the issue of payment of debts with the city and regional akimats, regional departments, which are obliged to report on the work once a month.

First deputy head of the region entrusted the Department of Energy to finalize the algorithm of debt collection and akims of the cities and areas to complete preparation for the heating season until the end of the week, provide people with heat and hot water as well as control the issue of providing social facilities with fuel.